ANALISIS KETERLAMBATAN SISTEM MANAJEMEN PEMBAYARAN TERMIN DARI PEMILIK PROYEK KEPADA KONTRAKTOR

(Studi Kasus : Proyek Pembangunan Pasar Umum Gianyar)

  • Ida Bagus Ketut Surya Suniarta Program Studi Teknik Sipil, Fakultas Teknik, Universitas Hindu Indonesia
  • I Wayan Muka Program Studi Teknik Sipil, Fakultas Teknik, Universitas Hindu Indonesia
  • I Nyoman Suta Widnyana Program Studi Teknik Sipil, Fakultas Teknik, Universitas Hindu Indonesia
Keywords: Factor Analysis, late payment of term, fees

Abstract

In general, every construction project has a plan and schedule implementation on time with the support of optimal resources.  To meet these objectives, one of the targets that must be met is the cost (budget) allocated and agreed upon by the project owner and the contractor to prevent late payment of the term.  The purpose of this research is to analyze the causal factors and priority factors of the occurrence of late payment of terms by the project owner to the contractor.  Type This study uses quantitative methods.  Processing of this data using the SPSS (Statistical Product and Service Solution) version of the computer program 17.00.  data analysis techniques, analysis techniques factor.  The results of this study explain the results of factor analysis for the variables in the study.  There are six factors that emerged from the analysis factors, namely Factor 1: Management Ability, Factor 2: Support Against Contractor, Factor 3: Understand Project Needs, Factor 4: Finance, Factor 5: Decision Making, and Factor 6 namely attitude.  Strategies and policies that can be done to overcome the problem of late payment of this term, then it is necessary to increase management capabilities in managing the project.

Downloads

Download data is not yet available.

References

Adimata, S. (2016). Analisis Keterlambatan Pembayaran Dalam Proyek Konstruksi Di Palangka Raya. Jurnal Perspektif Arsitektur, 11(01), 176–188. https://doi.org/1976

Ariffin, N. M., Sulaiman, Z., & Nasurdin, A. M. (2021). The effect of price, quality and brand image on customer satisfaction in the hotel industry. Tourism and Hospitality Research, 21(1), 119-133.

Arikunto, S. 2002. Metodologi Penelitian Suatu Pendekatan Proposal. Jakarta: PT. Rineka Cipta.

Asiyanto. 2005. Construction Project Cost Management. PT. Pradnya Paramita. Jakarta.

Christina, W. Y., Djakfar, L., & Thoyib, A. (2012). Pengaruh Budaya Keselamatan Dan Kesehatan kerja (K3) Terhadap Kinerja proyek konstruksi. Rekayasa Sipil, 6(1), 83–95. https://doi.org/193

Cleland, D. I., & King, W. R. 1987. Systems Analysis and Project Management. New York: Mc Graw-Hill.

Dimyati, Hamdan dan Nurjaman Kadar, 2014, Manajemen Proyek : CV Pustaka Setia.

Dipohusodo, I. 1996 “Manajemen Proyek dan Konstruksi” Jilid I, Penerbit Kanisius, Yogyakarta

Ervianto, W. I. 2005. Manajemen proyek konstruksi edisi revisi. Yogyakarta: Andi.

Fitriana, D., Y.K.O., F., H., J. U. D., & D.S., T. (2014). Pengukuran Kepuasan Kontraktor Terhadap Kinerja Klien Pada Proyek Konstruksi Swasta. Jurnal Karya Teknik Sipil, 3(1), 283–295.

Fretes. (2019, April 23). Analisis disparitas pembangunan ekonomi

antar wilayah di provinsi papua. Brawijaya Knowledge Garden. http://repository.ub.ac.id/id/eprint/189363/

Ikhsan, P. M., & Wirantina K, I. (2021). Analisis Faktor Risiko Keterlambatan Waktu Pada Proyek Lanjutan Pekerjaan Aksesibilitas Bandara Soekarno-Hatta (Doctoral dissertation, Institut Teknologi PLN).

Istiana, F. (2020). Pengaruh Kinerja Pelaksanaan Proyek Dengan Sistem Pembayaran Berdasarkan Termin Pada Proyek Konstruksi Bangunan Gedung di Provinsi DIY (Doctoral dissertation, INSTITUT Teknologi Nasional Yogyakarta).

Karim, M. S., Yusuf, J. E., & Rahman, M. H. (2021). Impact of Branding on Customer Satisfaction: A Study on Mobile Handset Industry in Bangladesh. Business and Economic Research, 11(2), 289-301.

Kusumah, W. E. (2020). Faktor-Faktor yang Mempengaruhi Keterlambatan Pembayaran Proyek Gedung di Kota Bandung. FTSP.

Laksono, T. D. (2007). Produktivitas Pada Proyek Konstruksi. Teodolita: Media Komunkasi Ilmiah Di Bidang Teknik, 8(2). https://doi.org/10.53810/jt.v8i2.17

Lee, H., Choi, S., & Lee, H. (2021). The relationship between product quality, perceived value, and customer satisfaction in the Korean online shopping mall industry. Journal of Retailing and Consumer Services, 60, 102434.

Lestari, S. D. (2019). Analisis Keterlambatan Pembayaran Termin Terhadap Operasional Pt. Galory Jasa Sarana Surabaya Periode 2014–2018 (Doctoral dissertation, STIE Mahardhika Surabaya).

Listanto, N., & Hardjomuljadi, S. (2019). Analisis faktor penyebab keterlambatan pembayaran kontraktor kepada subkontraktor pada proyek gedung bertingkat. Konstruksia, 10(1), 59-72.

Mardiana, L., & Fajri, R. (2021). The Effect of Training on Service Quality on Customer Satisfaction at Bank Syariah Mandiri Jambi. Jurnal Aplikasi Bisnis dan Manajemen, 7(1), 93-102.

R.J. Mockler (1972) dalam Soeharto (2005). Manajemen Konstruksi. Penerbit Rosdakarya : Bandung.

Raditya, A., Hardjomuljadi, S., & Amin, M. (2021). Faktor Dampak Keterlambatan Pembayaran Kontraktor Kepada Subkontraktor Pada Proyek Jalan Tol. Konstruksia, 13(1), 1–16. https://doi.org/10.24853/jk.13.1.1–16

Rani, N. M. S., & Yuni, N. K. S. E. (2021). Analisis Faktor Risiko Terhadap Keterlambatan Proyek Konstruksi the Himana Condotel. PADURAKSA: Jurnal Teknik Sipil Universitas Warmadewa, 10(1), 41-55.

Soeharto Iman. 1995. Manajamen Proyek Dari Konseptual sampai Operasional. Erlangga. Jakarta

Sugiyono. (2012). Metode Penelitian Kuantitatif, Kualitatif, dan R&D. Bandung: Alfabeta.

Sugiyono. (2014). Metode Penelitian Pendidikan Pendekatan Kuantitatif, Kualitatif, dan R&D. Bandung: Alfabeta

Suhartono, B., Budi, B., Siahaan, A., Nasution, I., & syukri, makmur. (2022). Analisis Metode dan Pendekatan dalam Manajemen Proyek pada Dunia Pendidikan. Edumaspul: Jurnal Pendidikan, 6(1), 25–31. https://doi.org/10.33487/edumaspul.v6i1.2809

Suliyanto, 2005, Analisis Data dalam Aplikasi Pemasaran, Bogor: Ghalia Indonesia

Supriyanti, D., Thoyib, A., & Unas, S. E. (2011). Relevansi PMBOK 2008 terhadap materi bidang manajemen konstruksi universitas brawijaya. Rekayasa Sipil, 5(3), 201–212. https://doi.org/206

Wahyuningtyas, A., & Waskito, J. P. H. (2021). Analisa Faktor–Faktor Penyebab Keterlambatan Proyek Pembangunan Jembatan Joyoboyo. axial: jurnal rekayasa dan manajemen konstruksi, 9(2), 071-078.

Wardana. (2021, February 1). TA: Faktor-Faktor Yang Mempengaruhi Keterlambatan Pembayaran Proyek Gedung Di Kota Bandung. Itenas Repository. http://eprints.itenas.ac.id/1468/

Published
2023-04-01
How to Cite
Suniarta, I. B. K. S., Muka, I. W., & Widnyana, I. N. S. (2023). ANALISIS KETERLAMBATAN SISTEM MANAJEMEN PEMBAYARAN TERMIN DARI PEMILIK PROYEK KEPADA KONTRAKTOR. Widya Teknik, 19(1), 23-29. https://doi.org/10.32795/widyateknik.v19i1.4146
Section
Articles