ANALISIS PRODUKTIVITAS TENAGA KERJA PADA PEKERJAAN PLAT LANTAI DENGAN METODE WORK SAMPLING

(Studi Kasus: Gedung Fakultas Kedokteran Universitas Udayana dan The Calna Villa)

  • I Nyoman Suta Widnyana Program Studi Teknik Sipil, Fakultas Teknik, Universitas Hindu Indonesia
  • I Putu Agus Ari Mahendra Program Studi Teknik Sipil, Fakultas Teknik, Universitas Hindu Indonesia
Keywords: Labor, Productivity, Work sampling

Abstract

Slab structure work in building construction is a very important job because floor slab work has a large volume. Labor productivity is very important in carrying out a job, the output of the construction sector can be seen from the quantity of work that has been done, while the input is the amount of resources used such as labor. The purpose of this study was to determine the amount of labor required for every 1 m2 (OH) and the standard time for labor productivity in completing 1 m2 of floor slab work. The method of collecting primary data is the source of research data obtained directly, such as the number of workers and observation of sampling data, while secondary data is obtained from projects such as working drawings. The data is then processed using Microsoft Excel. This research is a type of quantitative research with a work sampling method. The results of research on floor slab work in the Udayana University Faculty of Medicine Building Construction project show that the calculation of the volume of labor per day (OH) requires 0.011 OH masons and 0.011 OH workers and the results of calculating the standard time to complete 1 m2 of floor slab work is 3.15 minutes/m2 . The Calna Villa project shows that the calculation of The volume of labor (OH) requires 0.039 OH masons and 0.039 OH workers and the results of calculating the standard time to complete 1 m2 of floor slab work is 10.37 minutes/m2.

Downloads

Download data is not yet available.

References

Asroni, Ali. 2010. Balok dan Pelat Beton Bertulang. Yogyakarta. Graha Ilmu.

Ervianto,Wulfram. 2004. Pengukuran Produktivitass Kelompok Pekerja Bangunan Dalam Proyek Konstruksi (Studi Kasus Proyek Gedung Bertingkat di Surakarta). Jurnal Teknik Sipil Volume 9 No. 1, Universitas Atma Jaya, Yogyakarta.

Hasibuan Melayu. 1996. Organisai Dan Motivasi Dasar Peningkatan Produktivitas. Jakarta: Bumi Aksara.

Hutasoit. J. P. 2017. Analisis Produktivitas Tenaga Kerja Konstruksi Pada Pekerjaan Pasangan Lantai Kramik Dan Plesteran Dinding Menggunakan Metode Work Sampling. Jurnal Sipil Statik Vol.5 No 4 (205-214)

Muchdarsyah, Sinungan. 2003. Produktivitas apa dan bagaimana. Jakarta : Bumi Askara

Ravianto.J. 1981. Laporan II Dewan Produktivitas Nasional Dalam Produktivitas dan Tenaga Kerja, Dewan Produktivitas Nasional, Lembaga Informasi dan Produktivitas.

Soeharto, Iman. 1989. Manajemen Proyek : Dari konseptual Sampai Operasional. Jakarta : Erlangga

Sudarmoko, 1996. Diagram Perancangan Kolom Beton Bertulang, Jurusan Teknik Sipil, Fakultas Teknik, Universitas Gadjah Mada, Yogyakarta.

Sugiyono. 2013. Metode Penelitian Pendidikan Pendekatan Kuantitatif, Kualitatif, dan R&D. Bandung: Alfabeta

Sutalaksana, Anggawisastra, Tjakraatmadja. 1999. Teknik Tata Cara Kerja. T.I.- ITB. Bandung.

Walangitan, Ronny. 2012. Produktivitas Tenaga Kerja Dengan Menggunakan Metode Work Sampling Pada Pekerjaan Kolom Dan Balok Mega Trade Center Manado.

Shivam, N. 2014. Rating the Performance of Workers. Website : http://www.economicsdiscussion.net/engineeringeconomics/rating-the-performance-of-workers-6methods/21710

Published
2023-10-30
How to Cite
Widnyana, I. N. S., & Mahendra, I. P. A. A. (2023). ANALISIS PRODUKTIVITAS TENAGA KERJA PADA PEKERJAAN PLAT LANTAI DENGAN METODE WORK SAMPLING: (Studi Kasus: Gedung Fakultas Kedokteran Universitas Udayana dan The Calna Villa). Widya Teknik, 19(1), 29-34. https://doi.org/10.32795/widyateknik.v19i1.4478