ANALISIS DURASI DAN BIAYA DENGAN METODE RESOURCES LEVELING PADA PEMBANGUNAN BALAI SERBAGUNA BANJAR WONGAYA BETAN TABANAN

  • I Gede Ngurah Sunatha Program Studi Teknik Sipil, Universitas Mahasaraswati Denpasar
  • Anak Agung Ratu Ritaka Wangsa Program Studi Teknik Sipil, Universitas Mahasaraswati Denpasar
  • Tjokorda Istri Praganingrum Program Studi Teknik Sipil, Universitas Mahasaraswati Denpasar
  • I Nengah Sapta Widana Program Studi Teknik Sipil, Universitas Mahasaraswati Denpasar
Keywords: Metode Resources Leveling, Microsoft Office Project 2019, Overallocated, Human Resources

Abstract

In the Multipurpose Hall Advanced Development project in Banjar Wongaya Betan, Tabanan Regency, there was an overall allocation of human resources which caused a mismatch between plans and realization in the field, where implementation experienced delays in the 6th, 7th, and 8th weeks. Therefore, it is necessary to develop a human resource leveling method to minimize deviations between needs and the availability of existing human resources, namely by Resources Leveling using the help of Microsoft Office Project 2019. The Resources Leveling method is carried out by shifting non-critical activities within the available grace time so that available resources are not overloaded. This research aims to analyze the duration of activities and costs required for the project through descriptive research methods with a quantitative approach and using secondary data sources from the implementing contractor, namely CV. Sustainable Gold. Based on the analysis results, it was found that the number of human resources that were initially overallocated could be optimized after the leveling process was carried out using the resource leveling method with Microsoft Office Project 2019. The leveling process affected the project duration, from 90 days to 103 days. This is because of max. units of labor that the contractor is able to provide cannot meet the max. units required for project implementation. Meanwhile, the cost of human resources required is not affected by the leveling process, namely, it still costs IDR 71,981,700.

Downloads

Download data is not yet available.

References

Ahadzie, D.K., Proverbs, D.G. dan Lomolaiye, P.O. (2007) “Critical Success Criteria for Mass House Building Projects in Developing Countries,” International Journal of Project Management.

Ashworth, A. (1994) Perencanaan Biaya Bangunan. Jakarta: PT Gramedia Pustaka Utama.

Husen, A. (2009) Manajemen Proyek (Perencanaan, Penjadwalan, dan Pengendalian Proyek). Yogyakarta: Andi.

Kelana, R.P. (2010) “Optimalisasi Penggunaan Sumber Daya Manusia,” Jurnal Fakultas Teknik Universitas Sebelas Maret Surakarta.

Larson yang diterjemahkan oleh Dimyati, H. dan Nurjaman, K. (2014) Manajemen Proyek Pustaka Setia. Bandung.

Male, S. (2022) Resource Optimization Explained for Beginners, Runn. Tersedia pada: https://www.runn.io/blog/resource-optimization (Diakses: 25 April 2023).

Maromi, M.I. dan Indryani, R. (2015) “Metode Earned Value untuk Analisa Kinerja Biaya dan Waktu Pelaksanaan pada Proyek Pembangunan Condotel De Vasa Surabaya,” Jurnal Teknik ITS, 4(1).

Muzayanah, Y. (2008) Pemodelan Proporsi Sumber Daya Proyek Konstruksi. Tesis. Magister Teknik Sipil Universitas Diponegoro: Semarang.

Nurhayati (2010) Manajemen Proyek. Yogyakarta: Graha Ilmu.

Soeharto, I. (1999) Manajemen Proyek (Dari Konseptual Sampai Operasional). Edisi Kedua. Jilid 1. Jakarta: Erlangga.

Sunatha, I.G.N. dan Hermawan, I.P.Y. (2020) Modul Kursus Microsoft Project. Denpasar: Fakultas Teknik Universitas Mahasaraswati Denpasar.

Tiefensee, N. (2022) What is Overallocation of Resources & How to Avoid It, Runn. Tersedia pada: https://www.runn.io/blog/resource-overallocation (Diakses: 25 April 2023).

Widiantoro, O. (2017) Buku Ajar Rencana Anggaran Biaya (Contruction Cost Estimate). Surabaya: Jurusan Teknik Sipil Fakultas Teknik Universitas Negeri Surabaya.

Yanthi, N.P.L.M. (2022) Analisis Pengaruh Percepatan Waktu Pelaksanaan Terhadap Biaya Dengan Metode Fast Track Berbasis Ahadzie, D.K., Proverbs, D.G. dan Lomolaiye, P.O. (2007) “Critical Success Criteria for Mass House Building Projects in Developing Countries,” International Journal of Project Management.

Ashworth, A. (1994) Perencanaan Biaya Bangunan. Jakarta: PT Gramedia Pustaka Utama.

Husen, A. (2009) Manajemen Proyek (Perencanaan, Penjadwalan, dan Pengendalian Proyek). Yogyakarta: Andi.

Kelana, R.P. (2010) “Optimalisasi Penggunaan Sumber Daya Manusia,” Jurnal Fakultas Teknik Universitas Sebelas Maret Surakarta.

Larson yang diterjemahkan oleh Dimyati, H. dan Nurjaman, K. (2014) Manajemen Proyek Pustaka Setia. Bandung.

Male, S. (2022) Resource Optimization Explained for Beginners, Runn. Tersedia pada: https://www.runn.io/blog/resource-optimization (Diakses: 25 April 2023).

Maromi, M.I. dan Indryani, R. (2015) “Metode Earned Value untuk Analisa Kinerja Biaya dan Waktu Pelaksanaan pada Proyek Pembangunan Condotel De Vasa Surabaya,” Jurnal Teknik ITS, 4(1).

Muzayanah, Y. (2008) Pemodelan Proporsi Sumber Daya Proyek Konstruksi. Tesis. Magister Teknik Sipil Universitas Diponegoro: Semarang.

Nurhayati (2010) Manajemen Proyek. Yogyakarta: Graha Ilmu.

Soeharto, I. (1999) Manajemen Proyek (Dari Konseptual Sampai Operasional). Edisi Kedua. Jilid 1. Jakarta: Erlangga.

Sunatha, I.G.N. dan Hermawan, I.P.Y. (2020) Modul Kursus Microsoft Project. Denpasar: Fakultas Teknik Universitas Mahasaraswati Denpasar.

Tiefensee, N. (2022) What is Overallocation of Resources & How to Avoid It, Runn. Tersedia pada: https://www.runn.io/blog/resource-overallocation (Diakses: 25 April 2023).

Widiantoro, O. (2017) Buku Ajar Rencana Anggaran Biaya (Contruction Cost Estimate). Surabaya: Jurusan Teknik Sipil Fakultas Teknik Universitas Negeri Surabaya.

Yanthi, N.P.L.M. (2022) Analisis Pengaruh Percepatan Waktu Pelaksanaan Terhadap Biaya Dengan Metode Fast Track Berbasis Software Microsoft Project. Skripsi. Fakultas Teknik Universitas Mahasaraswati: Denpasar.

Published
2024-04-30
How to Cite
Sunatha, I. G. N., Wangsa, A. A. R. R., Praganingrum, T. I., & Widana, I. N. S. (2024). ANALISIS DURASI DAN BIAYA DENGAN METODE RESOURCES LEVELING PADA PEMBANGUNAN BALAI SERBAGUNA BANJAR WONGAYA BETAN TABANAN. Widya Teknik, 19(2), 47-53. https://doi.org/10.32795/widyateknik.v19i2.5856