ANALISIS FAKTOR PENYEBAB TERJADINYA (CCO) PADA PROYEK PEMBANGUNAN TEMPAT KULINER DAN POS JAGA TAMAN KOTA DENPASAR
Abstract
In implementing construction projects, problems are often faced, one of which is the occurrence of changes. This cannot be avoided on most projects due to the uniqueness of each project and limited time and costs in the planning process. For this reason, adjustments need to be made and this often results in changes in costs and changes in project implementation time. In turn, adjustments made must also be accommodated in administrative and contractual aspects in the form of a Contract Change Order (CCO). The aim of this research was to determine the factors that cause CCO, and to find out the factors that cause CCO that are most dominant in the implementation of construction projects for culinary establishments and park guard posts in the city of Denpasar. This research uses a quantitative descriptive method, where there are 41 factors that cause CCO. The data analysis method was carried out using the cut off point method. The results of the research show that there are 33 factors that cause CCO in the construction of culinary establishments and guard posts identified from the results of literature studies, interviews and questionnaires with 30 respondents, and the most dominant factors that cause CCO are found to be 11 factors out of 33 factors- The most dominant factor causing CCO. Of the 11 factors, the highest average value is in variable X41, namely changes in quality and material specifications of 3.87 and the lowest is in variable.
Downloads
References
Alaryan, A., Elbeltagi E., Elshahat, A., & Dawood, M. (2014). Causes and Effects of Change Orders on Construction Projects in Kuwait. Int. Journal of Engineering Research and Applications,. 4(7).
Bagus, I., Surya Suniarta, K., Muka, W., Nyoman, I., & Widnyana, S. (2023). Analisis Keterlambatan Sistem Manajemen Pembayaran Termin Dari Pemilik Proyek Kepada Kontraktor (Studi Kasus?: Proyek Pembangunan Pasar Umum Gianyar). In Jurnal Widya Teknik (Vol. 19, Issue 1).
Ervianto, & Wulfram I. (2002). Manajemen Proyek Konstruksi (Andi, Ed.). Yogjakarta.
Gumolili, S. A., Dinas, S., Dan, P., Pemprov, E., Sompie, S. B. F., & Rantung, J. P. (2012). Analisa Faktor-Faktor Penyebab Change Order Dan Pengaruhnya Terhadap Kinerja Waktu Pelaksanaan Proyek Konstruksi Di Lingkungan Pemerintah Provinsi Sulawesi Utara. Jurnal Ilmiah MEDIA ENGINEERING, 2(4).
H. Syamsunie Carsel HR. (2018). Metode Penelitian Kesehatan dan Pendidikan (Andi Adriani, Ed.; 1st ed.). Penebar Media Pustaka.
Hanna, A. S. N. E. V. , Camlic, R., Peterson, P. A., & ordheim, E. V. (2002). Kuantitative Definition of Projects Impacted by Change Orders, Journal of Construction Engineering and Management. 128.
Helsa Utra Achintya, & Tsulis Iq’bal Khairul Amar. (2023). FAKTOR Penyebab Terjadinya Contract Change Order Pada Proyek Pembangunan Jalan Gedong – Kerjo Kidul. Prosiding Seminar Nasional Teknik Sipil 2023 Fakultas Teknik Universitas Muhammadiyah Surakarta.
Hinze J. (2001). Construction Contracts. McGraw Hill. Second Edition.
Maulana. (2016). Faktor Penyebab Terjadinya Contract Change Order (Cco) Dan Pengaruhnya Terhadap Pelaksanaan Proyek Konstruksi Pembangunan Bendung (Vol. 02).
Nur Sahid. (2019). Kajian Faktor-Faktor Penyebab Cost Overrun Pada Proyek Konstruksi Jalan Dengan Apbd Kabupaten Sukoharjo. Jurnal Teknik Sipil Universitas Syiah Kuala, 2(8).
Putu, I. A., Mahapatni, S., Putra, C., & Murwanta, K. E. (2022). ANALISIS Kinerja Waktu Dan Biaya Pelaksanaan Proyek Dengan Metode Earned Value Pada Proyek Pembangunan Jembatan Pangkung Dalem Ruas Jalan Gitgit-Wanagiri. Jurnal Ilmiah Kurva Teknik, 11(2). https://e-journal.unmas.ac.id/index.php/jikt
Rizal, M. Abdullah., & Afifuddin, M. (2015). Kajian Pengaruh Change Order Pada Kinerja Pemerintah (Studi Kasus Pembangunan Rumah Komplek Meuligoe Wali Nanggroe. 4, 63–72.
Sandyavitri, A. (2009). Manajemen Resiko Di Proyek Konstruksi. MEDIA KOMUNIKASI TEKNIK SIPIL, 17, 23–38.
Sugiyono. (2016). Metode Penelitian Kuantitatif, Kualitatif, dan Kombinasi. Bandung: Alfabeta.
Widhiawati, I. A. R., Wiranata, A. A., & Wiawan, I. P. Y. (2016). Faktor-Faktor Penyebab Change Order pada proyek Konstruksi Gedung. Jurnal Ilmiah Teknik Sipil, A Scientific Journal Of Civil Engineering, 20, 1411–1292.